22.36.010
ESTABLISHMENT OF ADMINISTRATIVE OFFICER
The
provisions of this Ordinance shall be administered
by the Building Official or such other official
designated by the Village Manager. The Building
Official shall have the power to:
a.
Grant Certificates Of Occupancy.
b.
Make inspections of buildings and premises necessary
to carry out the duties of the enforcement of this
Ordinance.
c.
Issue building permits.
22.36.020
BUILDING PERMIT APPLICATION
a.
No building or structure within the Village of Beverly
Hills shall hereafter be erected, moved, repaired,
altered or razed, nor shall any work be started
to erect, move, repair, or raze until a building
permit shall have been obtained from the Building
Official, nor shall any use be added to an existing
use, nor shall any change be made in the use of
any building or land without a building permit having
been obtained from the Building Official, except
that no building permit shall be required for nonstructural
alterations costing less than five hundred dollars
($500.00). No such building permit shall be issued
to erect a building or structure or make any change
of use of a building or land unless it is in conformity
with the provisions of this Ordinance and all amendments
hereto. Unless construction is started within six
(6) months after the date of issuance of a building
permit, the building permit shall automatically
become void and fees forfeited. The Building Official
may reinstate a building permit that has become
void for failure to commence construction without
payment of further fees at his discretion as long
as site plan approval, if required, has not expired.
Fees for inspection and the issuance of permits
or certificates or copies thereof required or issued
under the provisions of this Ordinance shall be
collected by the Building Official in advance of
issuance. The amount of such fees shall be established
by resolution of the Village Council.
b.
The Building Official shall record all nonconforming
uses for the purposes of carrying out the provisions
of Section 22.30 hereof.
c. The Building Official shall not refuse to issue
a permit when conditions imposed by this Ordinance
are complied with by the applicant despite violations
of contracts, such as covenants or private agreements
which may occur upon the granting of such permit.
d.
The Building Official shall issue appearance tickets
for violations pursuant to this Ordinance.
e.
The Building Official shall require that all applications
for building permits be accompanied by plans and
specifications including a plot plan in duplicate,
which shall agree with the site plan approved by
the Village Council, when required, under Section
22.08.290 of this Ordinance. The plot plan shall
be prepared, signed, and sealed by a registered
professional civil engineer or a registered professional
land surveyor, and shall show the following:
1.
Legal description of the property and a statement
affirming that the property has been surveyed and
that the boundary corners of the property have been
marked by placing permanent points at each corner
of the property.
2.
North point and scale of not less than 1" =
100'.
3.
Exact dimensions of the property including bearings
and distances as described in the legal description.
4.
Property relationship of subject property with all
abutting property lines.
5.
Two foot contours or pegged grade elevations at
fifty feet (50') on center for the entire property
and for a distance not less than fifty feet (50')
outside the entire perimeter of the property.
6.
The existing finish grade elevations of all existing
buildings or structures on or within fifty feet
(50') of the property.
7.
The location of all existing and/or proposed drives
and parking areas.
8.
The location of all existing or proposed underground
utilities.
9.
Proposed finished grade of all buildings, the site
itself, and the entire perimeter of the property
including property corners.
10.
The location and widths of all existing and/or proposed
rights-of-way and/or easements and all abutting
streets and alleys.
11. The point, area, ditch, or enclosure to which
storm water is to drain, including discharge of
sump pumps.
12.
The location of the existing and/or proposed buildings
on the property shall be clearly shown and shall
include the dimensions to front, side, and rear
property lines and ties from the proposed building
to any adjoining building on or within fifty feet
(50') of the proposed building.
13.
Such other information concerning the lot or adjoining
lots as may be essential for determining whether
the provision of the Ordinance are being observed.
14.
Prior to pouring concrete for any footings, the
builder shall demonstrate to the Building Official
that the footing forms are properly located on the
lot and that the footing grade is set to the proper
elevation, both according to the dimensions and
elevations as indicated on the plot plan. One copy
of the plans shall be returned to the applicant
by the Building Official, after the Building Official
shall have marked such copy either as approved or
disapproved. The remaining copy shall be retained
in the office of the Building Official.
f.
Upon the completion of the work authorized by a
building permit, the holder thereof shall seek final
inspection thereof by notifying the Building Official
who shall then make final inspection promptly.
g.
Whenever the building, land and uses thereof as
set forth in the application are in conformity with
the provisions of this Ordinance it shall be the
duty of the Building Official to issue within seven
(7) working days after the receipt of said application
a building permit, and when such permit is refused,
to state such refusal in writing with the reasons
therefore.
h.
Whenever the application for a building permit involves
an addition or alteration to an existing building
or structure, the Building Official may waive the
requirements herein of the furnishing of a plot
plan when he determines that the public health,
safety and welfare will not be adversely affected
by doing so.
22.36.030
CERTIFICATE OF OCCUPANCY
No
land, building, structure, or part thereof shall
be occupied by or for any use for which a building
permit is required by this Ordinance unless and
until a Certificate of Occupancy shall have been
issued for such new use. The following shall apply
in the issuance of any certificate:
a. Certificates not to be Issued. No Certificates
of Occupancy pursuant to the Building Code of the
Village of Beverly Hills shall be issued for any
building, structure or part thereof, or for the
use of any land, which is not in accordance with
all provisions of this Ordinance.
b.
Certificates Required. No building or structure,
or parts thereof, which is hereafter erected or
altered, shall be occupied or used or the same caused
to be done, unless and until a Certificate of Occupancy
shall have been issued for such building or structure.
Such certificate shall not be issued until the following
requirements are complied with and are approved
by the Building Official.
1.
Prior to the official issuance of a Certificate
of Occupancy the Building Official shall inspect
the site to determine if the grading is in accordance
with the approved plot plan. If, in the judgment
of the Building Official, there is doubt that such
grading is in accordance with the plot plan, the
Building Official shall request a grading certificate
prepared, signed and sealed by a registered professional
civil engineer or a registered professional land
surveyor be submitted to the Building Official,
in duplicate, attesting to the fact that the site
has been constructed and graded in accordance with
the plot plan, permanent irons at each lot corner
are in evidence, and that the drainage pattern is
in accordance with the plot plan as approved at
the time of issuance of the building permit.
2.
In lieu of a grading survey, a surety bond, letter
of credit, or cash deposit in an amount set by the
Building Official may be required to insure grading
and submission of such survey at a later date when
a building, land or structure is otherwise suitable
for occupancy during that season of the year when
weather conditions make finish grading unfeasible.
In such case a temporary Certificate of Occupancy
may be issued and the date for completion of grading
shall be indicated on the temporary Certificate
of Occupancy or its related documents.
c.
Certificates Including Zoning. Certificate of Occupancy
as required by the Building Code for new buildings
or structures, or parts thereof, or for alterations
to or changes of use of existing buildings or structures,
shall also constitute Certificate of Occupancy as
required by this Ordinance.
d.
Certificates for Existing Buildings. Certificates
of Occupancy will be issued for existing buildings,
structures, or parts thereof, or existing uses of
land, if after inspection it is found that such
buildings, structures, or parts thereof, or such
use in land are in conformity with the provisions
of this Ordinance.
e.
Temporary Certificates. Nothing in this Ordinance
shall prevent the Building Official from the issuing
of a temporary Certificate of Occupancy for a portion
of a building or structure in process of erection
or alteration, provided that such temporary certificate
shall not be effective for a period of time in excess
of six (6) months nor more than five (5) days after
the completion of the entire building, to a state
ready for occupancy, and provided further that such
portion of the building, structure, or premises
is in conformity with the provisions of this Ordinance.
f.
Records of Certificates. A record of all certificates
issued shall be kept on file in the office of the
Building Official, and copies shall be furnished
upon request to any person.
g.
Certificates for Dwelling Accessory Buildings. Buildings
accessory to dwellings shall not require separate
Certificates of Occupancy but may be included in
the Certificate of Occupancy for the dwelling when
shown on the plot plan and when completed at the
same time as such dwellings.
h.
Application for Certificates. Application for Certificates
of Occupancy shall be made in writing to the Building
Official on forms furnished by the Department, and
such certificates shall be issued if, after final
inspection, it is found that the building or structure,
or part thereof, or the use of land is in accordance
with the provisions of this Ordinance. If such certificate
is refused for cause, the applicant therefore shall
be notified in writing of such refusal and cause
thereof.
|